SPECIFICATIONS Flashcards Preview

LARE SECTION 4 > SPECIFICATIONS > Flashcards

Flashcards in SPECIFICATIONS Deck (53)
Loading flashcards...
1

A type of contract with which the design firm invoices on a cost basis up to a stipulated maximum dollar amount that cannot be exceeded.

Guaranteed Maximum Price (GMP)

2

A unit price bid that accurately reflects the actual anticipated price of each item of work to be performed.

Balanced bid

3

A surety instrument that guarantees to the owner that the bearer, if awarded the contract, will enter into a binding contract and provide all required bonds.

Bid Bond

4

A specification that is expressly restrictive in stating that only one or two products will satisfy the quality requirements, or is implied when performance is so narrowly prescribed that only one or two products will satisfy the requirement.

Closed Specification

5

A bid that is not prepared in earnest, but is presented to appear to be a serious bid. Such bids are usually generated through collaborative efforts with another bidder who does submit a serious bid.

Complimentary Bid

6

AKA Boilerplate: outlines the roles of the parties to a construction agreement and provide guidance concerning procedures to follow under varying circumstances.

General Conditions

7

A common procedure in which the owner of a project contracts with a single firm, often called a prime contractor, for its construction. This firm may contract with speciality contractors for portions of the work

General Contract Method

8

Guidelines or rules enumerated for bidders on a project concerning proper procedures for bid submittal and relevant project information

Instructions to Bidders

9

A means of notifying the contractor about the decision to award the contract and of specifying when the contract time will start.

Notice to proceed

10

An open or nonrestrictive specification in which a wide variety (three or more) of products are considered suitable.

Open specification

11

A surety instrument in which the faithful performance of a contractor is guaranteed up to the face value of the bond.

Performance bond

12

A descriptive requirement that states the results or the performance of the finished product rather than the specific methods and means used to construct the product.

Performance specification

13

A meeting between the owner, the general contractor, and the major subcontractors that takes place after the contract is awarded but before construction begins. This conference addresses various matters deemed to be of importance to the project.

Preconstruction conference

14

A closed specification that names a project made by a particular manufacturer.

Proprietary specification

15

A performance specification that defines the acceptable product in terms of its ability to satisfy a standard developed by one of several standards organizations.

Reference specification

16

A bid that conforms to the standards outlined in the instruction to bidders. Only such bids can be considered on public works projects to assure all bidders of fair and equal treatment.

Regular bid

17

A compilation of general conditions, technical specifications, and other requirements that an agency uses on numerous construction projects. Such documents are prepared by state departments of transportation and many major municipalities.

Standard Specifications

18

A document that provides the qualitative requirements for a project in terms of materials, equipment, work performed, and so forth.

Technical Specifications

19

A unit price bind in which the pricing of the various items of work does not reflect the actual anticipated costs, but redistributes those costs to serve a specific objective of the bidder.

Unbalanced Bid

20

A contract in which payment is based on a contractor’s quoted price per unit of work performed and the owner’s measurement of the total number of such units installed.

Unit Price Contract

21

A contract in which the contractor is reimbursed for specified incurred costs, with an additional allowance provided for overhead and profit

Cost-Plus Contract

22

A contract in which the contractor agrees to construct a project for a specified sum of money.

Fixed-Price Contract / Lump Sum Contract

23

1. Agreement
2. Conditions
3. Drawings
4. Specifications
5. Adenda
6. Misc. documents associated w/ the contract bw the owner and contractor

Elements of the Contract Documents (according to AIA 201-207)
(6)

24

In the event of conflicting information between specifications and drawings...

Specifications supersede drawings
(CLARB / LARE answer)

25

Components of a three-part specification

Part 1: General
Part 2: Product / Materials
Part 3: Execution

26

Tech Spec Section
PART 1: General

Defines the scope and the ground rules for work to be performed

Lists reference specs (ASTM, etc)

May list related work, required submittal requirements, quality control or quality assurance requirements, warranty, manuals, product handling requirements

27

Tech Spec Section
PART 2: Product / Materials

The specific materials and products to be used

May outline the performance requirements of each product or manufacturing / fabrication processes to be used in production

Any products specified should be accompanied with an “approved equal” or similar language to keep the spec “open”

28

Tech Spec Section
PART 3: Execution

Describes the actual means of preparing, installing, or constructing the item in question, as well as any quality or performance requirements (testing) expected

29

3 Primary Specification Types

Performance
Prescriptive
Proprietary

30

Specifies the operational requirements of a component or installation; contractor is not instructed on how to accomplish the task, only how the component must function / perform

Performance Specification