What activity is performed in a routing?

Component assignment

62

What data is maintained in a work center?

Capacity formula

People assignments

63

Which of the following master data is assigned to a work center?
* material master
* cost center
* bill of material

Cost center

64

T/F
In the relationship between the different master data that are used in the plan to produce business process bill of material components are assigned to a routing operation.

True

65

T/F
In the relationship between the different master data that are used in the plan to produce business process a work center is assigned to a routing operation

True

66

T/F
In the relationship between the different master data that are used in the plan to produce business process a material master is assigned to a work center

False

67

T/F
In the relationship between the different master data that are used in the plan to produce business process a bill of material is assigned to a work center

False

68

What is the purpose of an activity type?

To allocate the costs of work performed by the cost center.

69

T/F
Marking a standard cost estimate reevaluates on hand inventory

False

70

T/F
Saving a cost estimate automatically updates the standard price in the material master

False

71

Planned independent requirements directly lead to ______________ when material requirement planning (MRP) is carried out.

Planned orders for in house production

Dependent requirements for in house production

72

Which of the following can be created by processing MRP (material requirement planning)
* purchase order
* dependent requirements
* planned orders
* planned independent requirements

Dependent requirements

Planned orders

73

Which of the following control parameters for MRP are required when you start the planning run
* processing key
* planning mode
* requirements grouping

Processing key

Planning mode

74

T/F
The MRP list represents the most up to date version of the planning scenario.

False

75

Name three steps that occur in production order processing

Order release

Variance calculation

Material staging

76

Name two elements of a production order

Components list

Operations

77

For final production execution, the planned order is converted into a _________________.

Manufacturing order

78

If a production order has the created status, which of the following actions can be performed for the order?

Check material availability

79

Name two steps performed after releasing an order

Material withdrawal

Printing the documents

80

A goods issue for a production order is posted in the system. What are the effects of the goods issue?

A controlling document is created

Inventory reservations are decreased

81

A goods receipt is posted in the system. Name two documents that are created.

Material document

Accounting document

82

Name two examples of transfer postings

Material - to - material

Stock - to - stock

83

T/F
A physical movement of stock is characteristic of a stock transfer posting.

True

84

Name two period end closing activities for production orders

Order settlement

Variance calculation

85

T/F
Variance calculation is a period-end activity

True

86

In MRP what kind of element is a sales order?

Demand element

87

How does controlling integrate with production?

A production order collects actual costs

A cost center is assigned to a work center

88

What documents does the order to cash business process include?

Sales order

Billing

89


Name four things a sales organization is responsible for

Distribution of goods and services
Negotiating sales conditions
Customers right of recourse
Product liability

90

A shipping point is a physical space and is near the __________

Delivering plant