30

According to the contract documents, contract time ends at the date of

Substantial completion

31

In general what is the minimum amount of time in architects should give contractors to prepare a bid?

Two weeks

32

According to Gen. conditions contractor must request a change in the contract sum with in

21 days

33

And agreements under which one party guarantees to make good to another party the debt, default, or failure to perform of a third-party. Also called a surety bond.

Bond

34

The bond obtained by contractor or owner, which guarantees of the project will be completed free of liens.

Completion bond

35

The type of surety obtained by the contractor. It's for the protection of the owner and is used to help ensure that the work will be completed in accordance with the contract documents.

Performance bond

36

A written promise or bond by a person or entity guarantees the performance of an obligation of another party. It can protect an owners interest by ensuring the contractor fulfills the requirements of the contract documents.

Surety

37

Is surety in the form of the forfeiture bond that is required by public agencies and some private owners. This submitted with the bed and guarantees the better, before to the contract, Blanchar into the contract within a specific time, and in accordance with the requirements of the bidding documents. These bonds are usually made for 5 to 10% of the bid amount and are activated if the selected bidder refuses to sign the contract.

Bid bond

38

Hey Bond acquired by the contractor in which the contractor and the contractors Serdy guaranteed to pay their subcontractors and purchase materials for the construction in accordance with the contract documents.

Labor and material payment bond (A312)

39

Minimum wheelchair passage width

32 inches at a point and 36 inches continuously

40

Width for wheelchair passing

Minimum for two wheelchairs to pass is 60 inches

41

Wheelchair turning space

To make 180° turn is a clear space of 60 inches

42

Minimum ground space to accommodate a single stationary wheelchair and occupant

30" x 48"

43

What slope constitutes a ramp

Greater then 1:20

44

The cross slope of an accessible route cannot exceed

1:50

45

It's an accessible route has changes in level greater then _____ a curb ramp, ramp, elevator, or platform lifts shall be provided.

1/2"

46

Minimum clearance width of a stairway adjacent to an area of rescue assistance..

48 inches between handrails

47

Circulation spaces shall have minimum clear headroom of...

80 inches

48

Maximum slope of a ramp in new construction...

1:12

49

The maximum rise for any ramp run ...

30"

50

The landing shall be at least as wide as ...

The ramp run leading to it

51

The landing length is be a minimum of

60 inches clear

52

If ramps change direction at landings, the minimum landing size is

60" x 60"

53

A ramp requires handrails on both sides if it has arise greater than ____ or horizontal projection greater than ___.

6" rise or 72" horizontal

54

Stairways she'll have handrails...

At both sides of all stairs

55

Handrails are continuous or extend at least ___ beyond the top riser and ___ plus the width of one tread the on the bottom riser.

12"

56

The clear space between handrails and wall is min ___.

1 1/2"

57

Top of the handrail shall be mounted between...

34" and 38" above the stair nosing

58

Torrential have a minimum clear opening of ___ with the door open 90°, measure between the face of the door and the opposite stop

32"

59

Doors not requiring full user passage, such a shallow closets may have to clear opening reduced to

20"