What are the KEY Inputs to Develop Project Charter (Initiate) (3)?

A

Project Statement of Work (SOW)
Business Case
Agreements
(EEF & OPA are the others)

1
Q

What is the KEY Tool & Technique for Develop Project Charter (Initiate) (1)?

A

Expert Judgement

Facilitation Techniques is the other

2
Q

What is the KEY Tool & Technique for Develop PMP (Planning) (1)?

A

Expert Judgement

Facilitation Technique is the other

3
Q

What is the KEY Input in Develop PMP (Planning) (1)?

A

Outputs from the other processes

Project Charter, EEF, OPA

4
Q

What are the KEY Outputs to Direct and Manage Project Work (Execute) (2)?

A

Deliverables

Work Performance Data

5
Q

What are the KEY Tools & Techniques in Direct and Manage Project Work (Execute) (2)?

A

Project Management Information System (PMIS)
Meetings

(Expert Judgement is the other)

6
Q

What are the KEY Outputs to Monitor & Control Project Work (Monitor & Control) (3)?

A

Change Requests
Work Performance reports
PMP Updates

7
Q

What is the KEY Tools & Techniques to Monitor & Control Project Work (Monitor & Control) (1)?

A

Expert Judgement

8
Q

What is the KEY Output to Perform Integrated Change Control (PICC) (Monitor & Control) (2)?

A

Approved Change Requests

Change Log

9
Q

What are the KEY Inputs to the Perform Integrated Change Control (PICC) (Monitor & Control) (2)?

A

Work Performance Reports

Change Requests

10
Q

What are the KEY Outputs to the Close Project or Phase (Close) (2)?

A

Final product, service, or result

Organizational Process Assets (OPA) updates