Earned Value Flashcards

1
Q

what is earned value?

A

earned value, as a quantity,represents the amount of work achieved at any given point in time

  • every task in the project has an earned value associated with it at any given time
  • earned value of each task is zero at the start
  • when a task is complete, its earned value is declared to be the amount equal to the amount allocated to the task
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

how do you calculate earned value?

A

earned value = total budget x %complete

earned value (task) = total budget (task) x %complete (task)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

PC =

A

planned cost the amount that is planned to have spent at any particular time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

AC =

A

actual costs of the work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

How is EV used?

A
  • record is made of each task and progress made (% complete)
  • EVs are calculated and added up
  • ACs are recorded and added up
  • Plotted against Planned cost (PC) on S-curve)
  • This can show whether project is on time/on budget
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

what three variances can be calculated from EV data

A

CV = cost variance SV (cost) = schedule variance SV (time) = schedule variance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

what is CV

A

the difference between the value of the work performed and the money spent on it CV = earned value - actual costs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

SV (cost)

A

difference between what was planned to have been achieved in terms of value delivered and what has actually been achieved
SV (cost) = earned value - planned cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

SV (time)

A

shows how far behind (or ahead) the project or activity is, compared to what was planned SV (time) = original duration - time now

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

what are performance indicies?

A
  • when quantities used to calculate variances are combined to give performance indicies
  • e.g. CPI - cost performance
  • SPI (cost-based) -schedule performance
  • value close to 1.0 represents planned situation
  • value < 1 is a problem
  • value > 1 is desirable (better than planned)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

CPI =

A

CPI = earned value/ actual cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

SPI (cost based)

A

SPI (cost-based) = earned value/ planned budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

SPI (time)

A

SPI (time) = original duration/actual time achieved

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

what is forecasting ?

A

To predict the state of the project at completion using baseline plan and earned value data, principally one of the variances or performance indicies

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

advantages of EVA

A
  • shows time and cost on one report
  • trends can be identified and corrective action taken
  • cost and schedule variances can used for forecasting
  • enables calculation of overall % completion of project which is of interest to senior managers
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

limitations of EVA

A
  • analysis is only meaningful if baseline budget estimate is robust (a good representation of the work)
  • does not represent a full picture of how close the project is to fulfilling its objectives (e.g. meeting customer requirements)
  • over optimistic reporting on progress reports
17
Q

What is BAC?

A

Budget at completion

It is synonomous with total budget

Every Task, Workpackage and Project has its own BAC, which is the maximum amount of effort that the plan says will be used for its completion.

18
Q

The earned value of a task is calculated by which formula?

Select one:

A. Planned budget x percentage task complete.

B. Total task budget x percentage task complete.

C. Total project budget x percentage task complete.

D. Actual cost x percentage task complete.

A

B. Total task budget x percentage task complete

Remember, to get a statistic that reports progress, we need to compare it against a baseline figure. So we multiply % complete by baseline figure, (task budget).

19
Q

When would you use variances to forecast?

A

Assumption 1: things will go as planned

Use when less than 30% of project is done

20
Q

When would you use performance indicators to forecast?

A

Assumption 2: Things will go as they are going now

Data about performance will be representative of likely future

When over 30% of project is complete

21
Q

How to forecast final project duration using assumption 1

A

final project duration = planned project time - schedule variance

22
Q

How to forecast final cost and cost overrun using assumption 1

A

estimated final cost = budget - cost variance

cost overrun = estimated final cost - budget

23
Q

How to forecast final project cost using assumption 2 and overrun

A

final project cost = budget/CPI

overrun = esimated final cost - budget

24
Q

How to calculate final project duration using assumption 2

A

estimated final project duration = planned completion time / SPI(cost)