Cost IOT&T Flashcards Preview

Project Management Professional v5 > Cost IOT&T > Flashcards

Flashcards in Cost IOT&T Deck (8)
Loading flashcards...
0
Q

What is the KEY Tool & Technique for Estimate Costs (Planning) (1)?

A

Cost of Quality

1
Q

What are the KEY Inputs to Estimate Costs (Planning) (2)?

A

Scope Baseline

Risk Register

2
Q

What is the KEY Output to Estimate Costs (Planning) (1)?

A

Activity Cost Estimates

3
Q

What is the KEY Tool & Technique for Determine Budget (Planning) (3)?

A

Cost Aggregation
Reserve Analysis
Funding Limit Reconciliation

4
Q

What is the KEY Output for Determine Budget (Planning) (1)?

A

Cost Baseline

5
Q

What is the KEY Input to Control Costs (Monitor & Control) (1)?

A

Work Performance Data

6
Q

What are the KEY Tools & Techniques for Control Costs (Monitor & Control) (2)?

A

Earned Value Management

Forecasting

7
Q

What is the KEY Output for Control Costs (Monitor & Control) (1)?

A

Work Performance Information