CDs Vocab Flashcards Preview

ARE CDs > CDs Vocab > Flashcards

Flashcards in CDs Vocab Deck (141)
Loading flashcards...
1
Q

supervision

A

Direction of the work by the contractor’s personnel. Supervision is not the responsibility of the architect.

2
Q

bond

A

An agreement under which one party (the surety or bonding company) guarantees to make good to another party (the obligee or owner) the debt, default, or failure to perform of a third party (the principal or contractor).

3
Q

surety bond

A

An agreement under which one party (the surety or bonding company) guarantees to make good to another party (the obligee or owner) the debt, default, or failure to perform of a third party (the principal or contractor).

4
Q

multiple of direct personnel expense agreement

A

An agreement providing for payment for professional services based upon the direct personnel expense multiplied by an agreed factor

5
Q

bid

A

A proposal by a contractor to do the work required by the contract documents for a stipulated sum of money.

6
Q

reference specification

A

A specification which refers to quality standards established by recognized testing authorities or by the federal government

7
Q

contract documents

A

Working drawings, specifications, addenda, general conditions of the contract, supplementary conditions, and the owner-contractor agreement

8
Q

general contract

A

The agreement between the owner and the contractor for the construction of a project.

9
Q

deposit for bidding documents

A

A deposit of money required for each bidder as security for the bidding documents, to ensure the return of the documents by unsuccessful bidders

10
Q

certificate of substantial completion

A

A document prepared by the architect stating that the work is substantially complete, thereby establishing the date of substantial completion. It generally fixes the time within which the contractor must complete the unfinished work listed.

11
Q

percentage agreement

A

An owner-architect agreement under which the professional fee is based upon a percentage of the construction cost of the project

12
Q

construction change directive

A

A document signed by the owner and the architect, which authorizes a change in the work, the contract sum, or the contract time. It is used when there is not complete agreement on the terms of a change order.

13
Q

contract time

A

The period of time within which the work must be completed, as established in the contract documents.

14
Q

cash allowance

A

An amount not included in the contract sum to cover the cost of certain items not specified in detail. Hardware and other finish items are often handled in this manner.

15
Q

Master Format

A

A systematic listing of construction trades, materials, systems, and admin requirements published by CSI for the purpose of organizing construction specs.

16
Q

labor and material payment bond

A

A bond guaranteeing to the owner that the contractor will pay for all labor and materials used for the project

17
Q

open proprietary spec

A

A proprietary spec which names several acceptable materials, products, or systems, any of which may be used by the contractor

18
Q

closed proprietary spec

A

A proprietary spec which requires a particular brand or trade name and does not permit any substitution

19
Q

arbitration

A

An alternative to litigating a dispute, in which one or more arbitrators hears the evidence and renders a decision.

20
Q

date of substantial completion

A

The date, certified by the architect, when the construction is sufficiently completed, in accordance with the contract documents, so that the owner can occupy the project for the intended use.

21
Q

project manual

A

The manual prepared by the architect for a project, including the technical specs, bidding instructions and forms, general conditions, supplementary conditions, special conditions, and other legal and admin docs

22
Q

working drawings

A

The part of the contract docs, prepared by the architect, which graphically illustrates the construction required for the project

23
Q

single prime contract

A

A contract for building construction under which one prime contractor is responsible for the entire project, in contrast to having separate contracts.

24
Q

errors and omissions insurance

A

Insurance which financially protects an architect against claims for damages resulting from professional negligence. aka professional liability insurance

25
Q

professional liability insurance

A

Insurance which financially protects an architect against claims for damages resulting from professional negligence. aka errors and omissions insurance

26
Q

separate prime contract

A

One of several owner-contractor agreements for a project, each of which provides for constructing a major portion of the work (general construction, electrical, mechanical, etc) by a different contract.

27
Q

substitution

A

A material, system, or product proposed by a contractor as being equivalent to that required by the contract documents

28
Q

lowest acceptable bona fide bid

A

The lowest bid which complies with all the stipulated requirements.

29
Q

cost-plus-fee contract

A

An agreement under which the contractor, or the architect, is reimbursed for his or her costs, and in addition, is paid a fee for his or her services.

30
Q

prime contractor

A

Any contractor on a project who has a contract directly with the owner.

31
Q

schedule of values

A

A statement furnished to the architect by the contractor reflecting the amounts to be allotted for the principal divisions of the work. It serves as a guide for reviewing the contractor’s periodic applications for payment

32
Q

unit price

A

An amount, stated in $/unit, provided by the contractor with his or her bid for adding or deleting specific portions of the work

33
Q

descriptive spec

A

A spec which describes all product components, arrangements, assembly methods, properties, and other details and requirements.

34
Q

liquidated damages

A

A sum chargeable against the contractor as reimbursement for damages suffered by the owner b/c of the contractor’s failure to complete the work w/i a specified time

35
Q

Davis-Bacon Act

A

Federal legislation that requires the department of labor to set prevailing wages for government financed construction projects

36
Q

overhead expense

A

Indirect expense, that is, expenses indirectly incurred and not chargeable to a specific project aka indirect expense

37
Q

indirect expense

A

Indirect expense, that is, expenses indirectly incurred and not chargeable to a specific project. aka overhead expense

38
Q

progress payments

A

Payments made to the contractor during progress of the work on account of work completed and/or materials suitably stored

39
Q

construction budget

A

The sum established by the owner as available for construction of the project

40
Q

Division one

A

The general requirements division of the specs which establishes the admin and procedural duties of the contractor, architect, and owner during construction.

41
Q

extra services

A

Professional services rendered by the architect, upon the owners request, in addition to the basic services identified in the owner-architect agreement. aka additional services

42
Q

additional services

A

Professional services rendered by the architect, upon the owners request, in addition to the basic services identified in the owner-architect agreement. aka extra services

43
Q

CPM (critical path method)

A

A system of planning and scheduling construction operations which analyzes sequences and durations of time using network diagrams

44
Q

negligence

A

Failure to meet the ordinary standard of care expected of an architect or other professional in a specific circumstance

45
Q

liability insurance

A

Insurance which financially protects the insures against liability on account of bodily injury or property damage sustained by another

46
Q

surety

A

An individual or company that guarantees to make good to another party the debt, default, or failure to perform of a third party.

47
Q

due care

A

The requirement that a professional exercise reasonable ability and judgment in a specific circumstance, the absence of which constitutes negligence. aka standard of care

48
Q

standard of care

A

The requirement that a professional exercise reasonable ability and judgment in a specific circumstance, the absence of which constitutes negligence. aka due care

49
Q

hold harmless clause

A

A contractual obligation whereby one party agrees to guarantee another party against loss or damage from specified liabilities. aka indemnification

50
Q

indemnification

A

A contractual obligation whereby one party agrees to guarantee another party against loss or damage from specified liabilities. aka hold harmless clause

51
Q

fixed limit of construction cost

A

The maximum allowable cost of the construction work, as established in the owner-architect agreement

52
Q

addition (to the contract sum)

A

An amount added to the contract sum either by an accepted additive alternate or by a change order

53
Q

property insurance

A

Fire and property damage insurance for a project during construction, usually purchased by the owner. aka builders risk insurance

54
Q

builders risk insurance

A

Fire and property damage insurance for a project during construction, usually purchased by the owner. aka property insurance

55
Q

direct personnel expense (DPE)

A

Salaries and wages attributable to a specific project, plus benefits such as employment taxes, insurance, sick leave, holidays, vacations, pensions, and similar contributions and benefits.

56
Q

basic services

A

The architectural services normally required for a building project, usually consisting of sds, dds, cds, bidding or negotiation, and construction contract administration

57
Q

guaranteed maximum cost

A

An amount established in an agreement between an owner and a contractor as the maximum cost of performing specific work. aka upset price

58
Q

upset price

A

An amount established in an agreement between an owner and a contractor as the maximum cost of performing specific work. guaranteed maximum cost

59
Q

warranty

A

A legally enforceable assurance of the quality of materials and labor furnished for a project, or of the length of time that a project or a part thereof will perform satisfactorily. aka guarantee

60
Q

guarantee

A

A legally enforceable assurance of the quality of materials and labor furnished for a project, or of the length of time that a project or a part thereof will perform satisfactorily. aka warranty

61
Q

express warranty

A

A legally enforceable promise made by the warrantor

62
Q

observation

A

On-site examination of the contractor’s work by the architect to determine in general if it is proceeding in accordance with the contract documents

63
Q

comprehensive services

A

The architects basic services expanded to include certain additional services, such as programming, land use studies, and so on

64
Q

XCU

A

The exclusion from insurance coverage for liability arising out of (x) explosion or blasting (C) collapse of or structural damage to a building (U) underground damage caused by mechanical equipment

65
Q

completion bond

A

A bond obtained by the contractor or owner, which guarantees that the project will be completed free of liens

66
Q

performance bond

A

A bond which guarantees to the owner that the contractor will perform the work in accordance with the contract documents

67
Q

supplementary conditions

A

Part of the contract documents, prepared by the architect, which may modify provisions of the general conditions of the contract

68
Q

Pert

A

Acronym for project evaluation review technique. A form of network analysis developed for military work and similar to the critical path method.

69
Q

Bidding documents

A

The invitation to bid, instructions to bidders, bid form, and the contract documents.

70
Q

subrogation

A

The substitution of one entity for another with regard to legal rights

71
Q

incentive clause

A

A clause in a cost plus fee contract between the owner and contractor in which the savings between the gmc and the actual project costs are proportionally shared

72
Q

option

A

A choice given to the contractor to provide specified alternates without prior approval of the architect

73
Q

release of lien

A

A legal document signed by a supplier of material or labor for a project, which releases his or her mechanic’s lien against the property

74
Q

contingency allowance

A

An amount included in a construction budget, normally 5-10%, to provide for unforseen or unpredictable costs

75
Q

bonus and penalty clause

A

A provision in the construction contract for payment of a bonus to the contractor for completing the project prior to a specific date, and for a charge (penalty) against the contractor for failing to complete the project by that date

76
Q

subcontractor

A

One who has a contract w/a prime contractor to perform a portion of the work

77
Q

means of egress

A

The elements which comprise an exit to the outside, including aisles, corridors, doors and stairways

78
Q

float

A

The extra time available for a construction activity above its estimated time duration, w/o causing any delay of project completion

79
Q

general conditions

A

The part of the cds which states the rights, responsibilities, and relationships of the parties involved, usually by means of standard docs published by the AIA

80
Q

certificat of insurance

A

A memorandum which outlines the types and limits of the insurance coverages carried by the contractor for a project

81
Q

project representative

A

The architects rep at the site, who assists in the general admin of the construction contract for a project

82
Q

barrier-free provision

A

Regulations which provide for accessibility to buildings and sites for persons w/disabilities

83
Q

penalty

A

a charge against the contractor for failing to complete the project by a specific date

84
Q

record drawings

A

A term sometimes erroneously used to describe drawings revised to show changes made during construction.

85
Q

shop drawings

A

Drawings prepared by the contractor, subcontractor, manufacturer, or supplier, showing how specific portions of the work shall be fabricated and/or installed

86
Q

key plan

A

A small-scale plan of a building or complex of buildings

87
Q

specs

A

Part of the contract documents, comprising written descriptions of materials, construction systems, and workmanship

88
Q

alternate bid

A

A proposal by a bidder for an amount to be subtracted from or added to the base bid if the corresponding change in the work is accepted. This may be either a deductive or additive alternate

89
Q

NIC

A

Abbreviation for not-in-contract, referring to items neither furnished nor installed by the contractor

90
Q

Americans w/Disabilities Act (ADA)

A

Federal civil rights legislation which establishes the right of persons w/disabilities to equal access to sites and buildings and sets design guidelines for its implementation

91
Q

application for payment

A

A contractor’s written request for payment of the amount due on account of work completed and/or materials suitably stored on site.

92
Q

consultant

A

An engineer or other specialist retained by the architect to provide specified professional services to the architect which the architect is required to provide to the owner under the owner-architect agreement

93
Q

substantial completion

A

As defined in the AIA general conditions, completion of a project to the point where the owner can occupy all or designated portions of the work for the purpose for which it is intended

94
Q

program

A

A written statement of the owner’s conditions and requirements for the project

95
Q

fast-track

A

Describing a construction procedure in which construction on each phase of a project is begun when its design is completed, w/o waiting for overall project design completion

96
Q

superintendent

A

The contractor’s representative at the site

97
Q

contract sum

A

The total amount payable by the owner to the contractor, as stated in the owner-contractor agreement, for performing the work under the contract documents

98
Q

indirect expense

A

Overhead expense, that is, expenses indirectly incurred and not chargeable to a specific project. aka overhead expense

99
Q

overhead expense

A

Overhead expense, that is, expenses indirectly incurred and not chargeable to a specific project. aka indirect expense

100
Q

proprietary spec

A

A spec which calls for desired materials, products, systems, and equipment by their trade names and model numbers

101
Q

performance spec

A

A spec which defines products or systems by describing end results

102
Q

deductive alternate

A

A proposal by a bidder for an amount to be subtracted from the base bid if the corresponding change in the work is accepted

103
Q

construction management (CM)

A

Management services performed by the architect or others, over and above normal architectural services, that contribute to the control of time and cost in the construction project

104
Q

waiver of lien

A

A document by which one relinquishes the right of a mechanic’s lien against the property of another.

105
Q

lump sum contract

A

An agreement under which the architect or contractor is paid a specific amount as the total fee for services performed. aka stipulate sum contract

106
Q

stipulate sum contract

A

An agreement under which the architect or contractor is paid a specific amount as the total fee for services performed. aka lump sum contract

107
Q

trade discount

A

The difference between the list price and the actual price paid

108
Q

bid bond

A

A surety bond guaranteeing that the bigger will sign a contract, if offered, in accordance with his or her proposal

109
Q

insurance

A

Coverage by contract (insurance policy) whereby one party (the insurance company) agrees to indemnify or reimburse another (the insured) against loss from a specified hazard

110
Q

extra

A

An item of work involving additional cost

111
Q

post-completion services

A

Additional services rendered to the owner by the architect following actual completion of the project

112
Q

certificate for payment

A

A statement by the architect informing the owner of the amount due the contractor on account of work completed and/or materials suitably stored

113
Q

clerk of the works

A

The owner’s job site representative.

114
Q

statue of limitations

A

An ordinance which specifies the period of time w/i which legal action must be brought to obtain legal relief for damage or injury

115
Q

TQM (total quality mangement)

A

An approach to the deliver of goods or services in which quality is determined by customer satisfaction and conformance to requirements

116
Q

special conditions

A

Part of the contract documents, other than the general and supplementary conditions, describing unique conditions of a project

117
Q

workers comp insurance

A

Insurance which covers workers’ job-related injuries, usually required by law

118
Q

addenda

A

Statements or drawings which modify the basic contract documents after the latter have been issued to the bidders, but prior to taking of bids

119
Q

change order

A

A written order to the contractor, prepared by the architect, signed by the owner, contractor, and architect, which authorizes a change in the work, the contract sum, or the contract time

120
Q

direct expenses

A

Expense items directly incurred by or attributable to a specific project

121
Q

base bid

A

the sum of money stated in the bid for which the bidder offers to do the work, not including any alternate bids

122
Q

additive alternate

A

A proposal by a bidder for an amount to be added to the base bid if the corresponding change in work is accepted

123
Q

letter of intent

A

A letter signifying intention to enter into a formal agreement and setting forth the general terms thereof

124
Q

cds

A

working drawings and sepcs

125
Q

invitation to bid

A

An invitation to a selected list of contractors soliciting bids for a project

126
Q

instructions to bidders

A

instructions in the bidding documents for preparing and submitting bids for a project. aka notice to bidders

127
Q

notice to bidders

A

instructions in the bidding documents for preparing and submitting bids for a project aka instructions to bidders

128
Q

agent

A

one who acts on behalf of another

129
Q

work

A

all materials and/or labor required for a project

130
Q

approved equal

A

a material or method that is approved by the architect as being equivalent to what was originally specified

131
Q

final completion

A

The completion of all work in accordance with the terms and conditions of the contract documents

132
Q

mechanic’s lien

A

A claim on property by those who furnish material or labor for the construction of a building. Clear title to the property cannot be obtained until the claim is settled

133
Q

submittal

A

A shop drawing, project data, or sample submitted by the contractor to the architect for review prior to incorporation in the work

134
Q

certificate of occupancy

A

A document issued by the governing authority stating that a building complies with applicable laws and permitting occupancy for its designated use

135
Q

sick building syndrome

A

A term used to describe poor air quality, which can lead to discomfort and possibly disease

136
Q

estimate

A

A forecast of probably costs, as opposed to a firm bid

137
Q

project budget

A

The sum established by the owner as available for the entire project, including the construction budget, land cost, equipment cost, financing cost, cost of professional services, and contingency allowances

138
Q

advertisement for bids

A

Published public notice soliciting proposals for a construction project

139
Q

sample

A

A material or assembly submitted for the architect’s approval prior to manufacture or delivery to the project

140
Q

retainage

A

An amount withheld from each payment to the contractor in accordance with the terms of the owner-contractor agreement

141
Q

punch list

A

A list of items to be corrected or completed, which is provided by the contractor and usually expanded by the architect based on a detailed inspection of the work prior to substantial completion