Calculations for the CPM Flashcards Preview

Construction Project Management > Calculations for the CPM > Flashcards

Flashcards in Calculations for the CPM Deck (9)
Loading flashcards...
1

The earliest time at which an event can occur, considering the duration of preceding activities

Early Event Time (ET)

2

It is the latest time at which an event can occur if the project is to be completed on schedule

Late Event Time (LT)

3

Determines the early-start times of activities

Forward Path

4

Proceeds from the most left node in the network and moves to the right

Forward path

5

Determines the late finish (LF) times of activities by preceding ____ from the end node to the starting note

BACKWARD

6

Placed in the right side boxes adjacent to the nodes

LF Values

7

Determine the flexibility of an activity to be delayed

Float Calculations

8

done when forward path and backward path calculations are complete

Float Calculations

9

It is the CPM scheduling method for AON

Precedence Diagram Method