31

after first observing physical differences at site from contract documents, C has

21 days to alert A

32

C must submit qualifications of

superintendant to A / O, 14 days to review and object.

33

construction schedule is supplied to O / A for

information, not approval. b/c C is solely responsible for sequence / progress of Work

34

C supplies A for approval before commencement

Submittal Schedule

35

maintains documents @ site w/ current field changes

C, and supplies to A @ completion for asbuilt

36

C submitting shops to O / A

constitutes approval

37

Prescriptive Specification

look up

38

Performance Specification

look up

39

Indemnification

look up

40

O may allocate design services to C (ex. sprinkler)

to C's licensed design professional (for $ efficiency)

41

royalty and license fees

are included in the contract sum, C's responsibility

42

correction period

1 year from substantial completion

43

A not to give instruction to

C's employees @ site

44

A may _____ work

reject

45

O may _____ work

stop

46

Shop drawings, Product data, Samples are

not contract documents

47

B 352

Duties, Responsibilities and Limitations of Authority of the Architect's Project Rep

48

C's relationship to those employed under Sub's

Indirect Contract

49

Incase of C default, O may accept

1. assignment of subs
2. pay amounts past due
3. can pass subs to next contractor
4. but O retains payment obligations

50

Construction Change Directive

O + A
used in absence of total agreement
contractor must perform work
owner must pay

51

When a final sum of CCD is agreed

must be filed as a Change Order

52

A defines rental values of C owner equipement in contract docs

in order to prepare a cost for CCD incase C will not

53

G 710

Architects Supplemental Instructions

54

Minor Changes

1. consistent with design intent
2. no change to time/$

55

Contact time is

Agreement through Substantial Completion

56

Dote of Commencement

determined in Agreement, not actual start of construction

57

"time is of the essence"

delay is a breach of contract

58

Schedule of Values

- stipulated sum or GMP
- C submits to A breakdown of $ values per phase
- G703 Continuation Sheet

59

G 703

used to document SoV

60

Retainage located in documents

O / C agreement or Supplementary Conditions